Weight: 200 tonnes
Water depth: 23 m (75 ft)
Tanker Storage Capacity: 170,000 cubic meters
Contract awarded: Jan, 2013
Year of delivery: Nov, 2013
Scope of Work:
CDO is responsible for the construction and procurement of casting and forging components of the Tower Yoke Mooring System for the LNG Floating Terminal Project FSRU. The terminal will have a storage capacity of 170,000 cubic meters of LNG and a capacity to process 2 million tons of LNG per year.
This Tower Yoke Mooring System is DNV classed